TURNPIKE @ MIDWAY RD SOUTHERN RAMPS INTERCHANGE (MP 150)
Commenting is now closed, thank you for participating
Click on the map to change the street view. Street View may not appear if not available through Google Maps.
Coordinates: 27.37428491894315, -80.38369613736808
Project ID: 4518581
Lead Agency: MANAGED BY FDOT
From: SOUTHERN RAMPS INTERCHANGE
To: SOUTHERN RAMPS INTERCHANGE
Length: 0.8
Phase Group: PRELIMINARY ENGINEERING, RIGHT OF WAY, CONSTRUCTION
Contract Class: 7
Item Segment: 1
SIS: Yes
Component Group: TURNPIKE
Related Key: 4518581
LRTP: Page 3-9
County: ST. LUCIE
Agency: MANAGED BY FDOT
INTERCHANGE RAMP (NEW)
SISLead Agency: MANAGED BY FDOT
From: SOUTHERN RAMPS INTERCHANGE
To: SOUTHERN RAMPS INTERCHANGE
Length: 0.8
Phase Group: PRELIMINARY ENGINEERING, RIGHT OF WAY, CONSTRUCTION
Contract Class: 7
Item Segment: 1
SIS: Yes
Component Group: TURNPIKE
Related Key: 4518581
LRTP: Page 3-9
County: ST. LUCIE
Responsible Agency
Agency: MANAGED BY FDOT
Funding
Phase | Fund Code | 2024 | 2025 | 2026 | 2027 | 2028 | Total |
---|---|---|---|---|---|---|---|
PE | PKYI | 1,600,000 | 0 | 0 | 0 | 0 | 1,600,000 |
ROW | PKYI | 0 | 5,500,000 | 0 | 0 | 0 | 5,500,000 |
CST | PKYI | 0 | 0 | 0 | 12,852,872 | 0 | 12,852,872 |
1,600,000 | 5,500,000 | 12,852,872 | Total: 19,952,872 |
Prior Year Cost: 10,246
Future Year Cost: 0
Total Project Cost: 19,963,118
LRTP: Page 3-9